- March 18, 2025
- February 25, 2025
Start Date: On-going End Date: On-going
- February 20, 2025
Start Date: February 2025 End Date: September 2025 The work consists of providing all labor, materials, equipment, and incidentals necessary for the resurfacing along Goldenrod Road (SR 551) form Cargo Road to Lee Vista Boulevard and pavement markings from Cargo Road to Hoffner Avenue. Work also includes the replacement of guardrail, sidewalk replacement, pond regrading, […]
- January 14, 2025
Project start: January 2025 Project end: Mid-to late 2025
- November 20, 2024
The Florida Highway Patrol (FHP) and the Central Florida Expressway Authority (CFX) are expanding their partnership to launch the first-of-its-kind Desk Trooper, an innovative program enabling troopers to respond to minor car crashes virtually through interactive technology. Through the ‘Desk Trooper’ program, state troopers can interact virtually within minutes with those involved in a minor […]
The Central Florida Expressway Authority (CFX) is designing capacity improvements to State Road 528 / Beachline Expressway from Goldenrod Road to Innovation Way. The seven-mile project will add an additional lane in the eastbound direction of SR 528, expanding the roadway from two to three travel lanes. These capacity improvements projects will greatly increase ease […]
The Central Florida Expressway Authority (CFX) is currently designing a half interchange at SR 429 and Binion Road in Southwest Apopka. This half interchange will improve mobility by connecting a northbound on-ramp and a southbound off-ramp from SR 429 to Binion Road. Currently, in order to access SR 429 in Southwest Apopka, drivers must enter […]
- February 26, 2024
State Road 429 and State Road 414 The project consists of resurfacing SR 429 from Connector Road to Lust Road and SR 414 from SR 429 to west of Marden Road in Orange County. Lane closures and ramp detours will be scheduled during this project but will be done between 8 p.m. and 6 a.m., […]
- November 3, 2023
The Central Florida Expressway Authority has begun implementing Flex Lanes on State Road 417 and State Road 429, as part of the capacity improvement projects on those roadways. These lanes are the first of their kind in the Southeast. These innovative lanes use a wider median shoulder to allow traffic to continue flowing when an […]
- October 23, 2023
Start Date: October 2023 Anticipated End Date: Winter 2023
Start date: October 2023 Expected Completion date: Winter 2024
- September 26, 2023
The Central Florida Expressway Authority (CFX) is designing the State Road 414 Expressway extension. The 3.3-mile project will provide a direct connection between the eastern end of the SR 414 (John Land Apopka Expressway) and Interstate 4 (I-4). The project will improve system connectivity between SR 429 and I-4 to meet current and future traffic […]
- July 27, 2023
This project will provide median protection improvements on SR 429 from Seidel Road to Tilden Road and on SR 451 from Ocoee Apopka Road to Marshall Lake Road. The work includes constructing miscellaneous asphalt pavement and guardrail in the median and regrading the shoulder adjacent to existing concrete ditch pavement. Start Date: June 2023 Anticipated […]
The Central Florida Expressway Authority (CFX) has begun to design Phase 1 of State Road 534 (SR 534). This project is part of the Osceola County Expressway Authority’s (OCX) Master Plan adopted by CFX in 2016. SR 534 would form the northeastern section of the beltway around Osceola County. The new limited access expressway will […]
- April 7, 2023
This project is removing the bridge on SR 528 that runs over Farm Access Road 1. Start Date: November 2022 Anticipation Completion Date: Summer 2024
Project History In February 2021, CFX began the capacity improvements of the southern corridor of SR 417 from four to six lanes (three lanes in each direction) to improve traffic flow on one of CFX’s busiest expressways. The project is also adding wider median shoulders that can temporarily accommodate additional traffic during emergency response events, […]
- July 26, 2022
This project consists of removing and replacing three new 3-line DMS signs and sign structures along SR 417 and SR 528.
In August 2021, the Central Florida Expressway Authority (CFX), in partnership with Osceola County, began the design of the proposed capacity improvements of County Road 532/Osceola Polk Line Road from Lake Wilson Road to US 17/92. This is being done in conjunction with the planned extension of Poinciana Parkway from its northern end at Ronald […]
In February 2021, CFX began the capacity improvements of SR 538/Poinciana Parkway to create a divided four-lane expressway from Ronald Reagan Parkway to CR 580/Cypress Parkway. The newly improved parkway makes it easier and faster for residents to access regional transportation networks, theme parks, and the Orlando metro area. The 7-mile project began in February […]
The Central Florida Expressway Authority (CFX) is designing the extension of State Road 538/Poinciana Parkway. The extension is being designed in two segments. Segment 1, from Ronald Reagan Parkway to south of US 17/92 and Segment 2, from south of US 17/92 to County Road 532 are expected to improve traffic flow and operations in […]
The Central Florida Expressway Authority (CFX) is building the State Road 516 Lake/Orange Expressway in Lake and Orange counties. Built with innovation in mind, SR 516 will serve as a revolutionary testbed for electric in-vehicle charging. SR 516 will be the most sustainable project ever delivered by CFX. The new 4.4-mile expressway, which is being […]
In January 2022, CFX began the capacity improvements on SR 429 between Tilden Road and SR 414 to improve traffic flow and relieve congestion. These capacity improvements include expanding from four to six lanes (three lanes in each direction). CFX is also adding wider median shoulders that can temporarily accommodate additional traffic during emergency response […]
- September 15, 2017
The Central Florida Expressway Authority completed the State Road 417 (Central Florida GreeneWay) / State Road 408 (Spessard L. Holland East-West Expressway) Interchange. Phase one was the widening of State Road 417 between Berry Dease Road and State Road 408. The 1.6-mile project saw the addition of a travel lane in both directions (from three […]
The Central Florida Expressway Authority began widening State Road 417 from just south of Econlockhatchee Trail to the Orange/Seminole County line in September 2018. The 3.2-mile project added a travel lane in both directions, expanding the expressway from four to six lanes. The project also included eliminating one cash lane in each direction at the […]
- May 4, 2017
In May 2017, the Central Florida Expressway Authority (CFX) will begin field testing a new, state-of-the-art toll collection system at the State Road 414 (John Land Apopka Expressway) Coral Hills Main Plaza. The new system is designed to replace much of CFX’s existing toll collection system, some of which has been in service for over […]
- February 16, 2017
As part of our mission to ensure the safety of our customers, the Central Florida Expressway Authority (CFX) began work on its Wrong-Way Driving Prevention Program in 2012 in partnership with the University of Central Florida. The program was broken out into three phases. To date, we have 63 wrong-way ramp detection systems and 10 […]
To help reduce accident clearance times and improve safety, the Central Florida Expressway Authority (CFX) has partnered with the Florida Department of Transportation, MetroPlan Orlando, the Florida Highway Patrol, and the Orlando Police Department on a collaborative Pilot Project to research advanced technologies and methods for investigating crash scenes. The Crash Scene Investigation Pilot Project […]